Fire safety audits and NOC support
A clear, code-referenced view of where your building stands.
WATERWEB assesses buildings and facilities against the National Building Code (NBC), the applicable Indian Standards and, where relevant, National Fire Protection Association (NFPA) standards. It then supports owners through remediation and the fire authority's no-objection certificate (NOC) process, from pre-NOC review to inspection readiness.
Overview
Fire safety compliance in India is enforced through the fire NOC, periodic inspection and, increasingly, audits required of specific occupancies such as healthcare facilities. For owners and facility managers, the greatest risk is not knowing where a building stands until an inspector, an insurer or an incident reveals it.
A WATERWEB fire safety audit replaces that uncertainty with a prioritised, evidence-based plan. It examines not only the installed systems but the building itself: its means of escape, compartmentation, fire loads, electrical safety and emergency arrangements. Each deficiency is referenced to the clause it breaches and matched to a practical remedy.
17.2%
of fire-accident deaths in India in 2024 were attributed to electrical short circuits, which is why electrical safety forms part of every WATERWEB audit.

How it works
The audit begins with a review of approved drawings, previous NOCs and maintenance records, followed by a detailed site survey. WATERWEB tests representative systems in operation, evaluates means of escape and compartmentation, and assesses electrical and housekeeping risks. The findings are consolidated into a gap report ranked by priority, which forms the basis for remedial design, installation and, where required, the fire authority submission.
What the audit covers
- Means of escape
- Exits, staircases, travel distances, signage, emergency lighting and refuge areas.
- Active systems
- Hydrants, sprinklers, pumps, detection and alarm, and suppression systems, tested in operation.
- Compartmentation
- Fire-rated construction, doors, dampers and penetration seals.
- Electrical safety
- Distribution, isolation, cable management and backup power.
- Fire load and housekeeping
- Storage practices, combustible materials and ignition sources.
- Emergency preparedness
- Evacuation plans, drills, training and control room arrangements.
- Records
- Approvals, NOCs, test certificates and maintenance history.
Engagement types
| Engagement | Scope |
|---|---|
| Pre-NOC review | Design and documentation review before an application is submitted. |
| Gap assessment | An existing building measured against current requirements. |
| Pre-inspection readiness | Targeted verification ahead of a statutory or insurer inspection. |
| Post-notice remediation | A structured response to a notice from the fire authority or municipality. |
Deliverables
Gap report
Every deficiency, the governing clause and the remedy, ranked by priority.
Photographic evidence
Each finding photographed and located for follow-up.
Remediation plan
Works sequenced and budgeted so the building can stay in use.
Submission package
Drawings, schematics and documentation for the fire authority.
Close-out verification
Each item re-inspected and signed off once resolved.
Management briefing
A concise summary of risk and priorities for owners and boards.
Typical applications
- Before a fire NOC application for a new building
- Ahead of a high-rise biennial inspection
- Following a notice from the fire authority or municipality
- Before acquiring, leasing or changing the use of a building
A gap assessment is the most efficient way to anticipate the findings of a statutory inspection.
Scope of delivery
Document review
Approved plans, previous NOCs and maintenance records.
Site survey
Systems, means of escape, compartmentation and fire tender access.
Gap report
Findings reviewed with the owner and remedial works agreed.
Retrofit
Design and installation of the remedial works.
Submission support
Technical content of the NOC application, prepared for the owner to submit.
Owner responsibilities
Most audit findings trace back to missing records and routine items left to lapse. These habits keep a building ready for inspection between audits.
- Retain approved plans and previous NOCs on file
- Keep maintenance records current
- Keep exits, staircases and fire tender access clear
- Notify WATERWEB of any change of use or additional floor
Industries served
View projects
Commercial and residential buildings
Offices, residential towers, hotels and hospitals that must hold a fire no-objection certificate.

Manufacturing and engineering
Heavy engineering, automotive, paper and pharmaceutical facilities.

Government, defence and research
Launch pads, aircraft hangars, missile launch centres and research facilities.
Frequently asked questions
Does a gap assessment replace the fire authority's inspection?
No. Only Karnataka State Fire and Emergency Services can inspect for and issue the NOC. The assessment anticipates the authority's findings so that deficiencies can be resolved in advance.
How are fire NOC applications made in Karnataka?
Applications for high-rise buildings are submitted online through the state's Seva Sindhu portal, with site, floor, elevation and section plans, a fire schematic and supporting documents. WATERWEB prepares the technical content of the submission.
Can WATERWEB guarantee an NOC?
No firm can guarantee an NOC. WATERWEB prepares the technical drawings and documentation and supports the application; the decision rests with the fire authority.
What changed with NBCS 2026?
The Bureau of Indian Standards replaced NBC 2016 with the National Building Construction Standards in April 2026. Karnataka's legislation still refers to NBC 2016 and will do so until the state adopts the new standard. WATERWEB is tracking the transition.
Planning a new facility, or assessing an existing system?
A WATERWEB engineer will review your drawings or survey the site, assess it against the governing code and set out recommendations in writing.